HOMECOMPANY PROFILEPROJECTSRESOURCESNEWSCONTACT US
blog-articles
Sarawak Energy Bakun HEP Project: Delivering Innovation Through Challenges in the VAC System Implementation
Adelene Tie, January 15, 2025
Project Recap: Supply, Delivery, Installation, Testing, and Commissioning of VAC System at Sarawak Energy Bakun HEP

Introduction and Background

The Sarawak Energy Bakun Hydroelectric Plant (HEP) is one of Malaysia’s largest renewable energy projects, located in Sarawak. This facility plays a crucial role in providing sustainable energy to the region, powering industries and homes alike. As part of ongoing efforts to enhance its operational efficiency and safety, Sarawak Energy Sdn. Bhd. initiated the Bakun Pressurization Project in 2024. This project aimed to upgrade the current facility of their Ventilation and Air Conditioning (VAC) system, with a state-of-the-art Air Filteration Unit (AFU) Unit, ensuring optimal environmental conditions and advanced fire safety measures.

The project was a collaborative endeavor involving multiple stakeholders:

  • Main Contractor: United Credible Sdn. Bhd.
  • Instrument Contractor: Vision Air-Cond Services Sdn. Bhd.
  • Engineering Expertise: Maritime & Industrial Engineers Sdn. Bhd. and Ultech Engineering as sub-contractors, leading the design, installation, and commissioning efforts.

The initiative reflects Sarawak Energy’s commitment to leveraging cutting-edge technology to maintain world-class standards at its facilities. This project recap provides a detailed account of Ultech Engineering’s contributions, challenges faced, and solutions implemented to ensure the successful completion of the Bakun Pressurization Project.

Overview of the Sarawak Energy Bakun Pressurization Project

Ultech Engineering undertook the monumental task of supplying, delivering, installing, testing, and commissioning a VAC system at the Bakun Hydroelectric Plant (HEP). This ambitious project, commissioned in 2024, was designed to support Sarawak Energy Sdn. Bhd., with partnerships including United Credible Sdn. Bhd. as the main contractor and Vision Air-Cond Services Sdn. Bhd. as the instrumentation contractor.

Ultech Engineering Sdn. Bhd. participated in this project as a subcontractor along with Maritime & Industrial Engineers Sdn. Bhd. and this undertaking involved the supply, delivery, installation, testing, and commissioning of a VAC (Ventilation and Air Conditioning) system, more specifically the AFU (Air Filteration Unit) system at Bakun Hydroelectric Plant (HEP). The project’s successful completion stands as a testament to the technical prowess and dedication of the Ultech Engineering team.

Project Key Personnel and Scope

The project was spearheaded by Project Manager and Engineer Wang Zhi Xian, with support from team members, Automation and Control Engineers Ellysha Astin and Mike Gaby Law. Ultech Engineering’s primary responsibility was the design, installation, and commissioning of motor control cabinets, specifically the MCC-CCR and MCC-RIO1 panels. These were interfaced with three junction boxes and installed in both the control room and the VAC hall (outdoor).

The main project scope work included:

  • Wire termination at panels, junction boxes, and equipment.
  • Comprehensive operation testing.
  • Integration with SCADA and HMI systems.

Additional tasks included the delivery, supply, and installation of trunking/tray and cables, wire termination, and system rectification. While trunking/tray installation and cable laying were primarily managed by the partnering wiremen team, Ultech Engineering stepped in to support these efforts towards the project’s conclusion.

Project Objectives Deep Dive and Technological Explanations

The primary objective of the Air Filtration Unit (AFU) system is pressurization. When the system starts, the motor draws air into the room, with its speed modulated by the PLC to match the specified setpoint. For instance, if the Common Supply Air Pressure setpoint is 100 Pa, the motor speed adjusts accordingly. Should the duty motor be unable to reach the setpoint, the standby motor starts to support it and stops once the setpoint is achieved. Additionally, after a designated service duration, such as 1440 minutes, the duty motor will stop, and the standby motor will take over. This alternating operation ensures consistent performance and equipment longevity.

Automating the AFU Start and Stop Sequences

Start Sequence:

  1. Motorized damper opens.
  2. After 30 seconds, the motor starts.

Stop Sequence:

  1. Motor stops.
  2. Motorized damper closes.

Each AFU unit comprises two motors, two filter differential transmitters, two outlet motorized dampers, and one common supply air pressure sensor, all installed outdoors. A total of five AFUs were implemented in this project.

Commissioning of the MCC Panels

The Motor Control Center (MCC) panels play a crucial role in the system's functionality. These panels include circuit breakers, relays, fuses, PLC modules, and network switches, ensuring the seamless operation of the AFU system.

Challenges Encountered and Resolutions

Working in a remote and rural location like Bakun presents unique challenges that demand adaptability, resilience, and ingenuity. This project required Ultech Engineering’s team to navigate logistical constraints, communication barriers, and environmental factors, all while upholding the highest standards of engineering excellence. Despite these obstacles, the successful completion of the Bakun Pressurization project brought a profound sense of purpose and achievement to the entire team.

1. Adapting to Communication Hurdles

The multi-stakeholder nature of this project presented significant communication challenges. Ultech Engineering had to coordinate with:

  • Wiremen from the partnering team.
  • Other contractors.
  • The main contractor and clients.

To address this, the team maintained transparency by sharing daily site reports with pictures and frequent updates. This practice not only kept stakeholders informed but also ensured that client expectations were consistently met.

2. Addressing Weather Constraints

Outdoor tasks were frequently disrupted by adverse weather conditions. The team adapted by prioritizing indoor work during poor weather and rescheduling outdoor tasks for favorable conditions.

3. Solving Logistical Difficulties

The physical layout of the worksite posed logistical challenges. With tools and materials stored at the ground floor loading bay, team members often had to traverse significant distances to reach work locations such as the rooftop, jackroof, and the level 2 basement of the powerhouse. Strategic planning during general working hours (8 AM to 9 AM) helped minimize unnecessary movement and conserve energy.

4. Working on Accommodation Issues

The absence of nearby accommodations within the dam area added to the complexity. The team stayed in Sungei Asap, approximately 45 minutes to an hour away from Bakun Dam. This necessitated careful scheduling and efficient travel management.

5. Collaborating Despite Resource Shortages

Occasional shortages of tools and materials required the team to borrow equipment from contractors on-site. All borrowed items were promptly returned to maintain good working relationships.

Despite these challenges, the team’s determination and collaborative efforts enabled them to overcome obstacles effectively. The completion of the Bakun Pressurization project stands as a testament to Ultech Engineering’s adaptability and problem-solving prowess. Projects in such remote locations may be demanding, but they also inspire a deep sense of fulfillment, knowing that each milestone achieved contributes to the advancement of essential infrastructure in the region.

Technical Specifications and Client Feedback

Equipment and Systems Installed

In the Bakun Pressurization project, Ultech Engineering implemented advanced equipment to ensure efficient and reliable operation of the Air Filtration Unit (AFU) system. Ultech Engineering employed advanced technology, including:

  • Siemens Simatic ET200SP for modular automation.
  • PC for SCADA (Supervisory Control and Data Acquisition).
  • Siemens MTP1000 HMI for human-machine interfacing.

These systems were designed to:

  • Control outlet pressure for outgoing air supply using Variable Speed Drives (VSDs).
  • Operate motorized fire dampers for enhanced safety during fire emergencies.

Here's an overview of the key components:

SIMATIC ET 200SP Distributed I/O System

The SIMATIC ET 200SP is a versatile and compact distributed I/O system designed for efficient control in industrial settings. Its modular design allows for easy scalability and integration into various automation solutions. Key features include:

  • Compact Design: The ET 200SP's slim profile facilitates high packing density, making it suitable for installations with limited space. siemens.com Global Website
  • High Performance: With internal data transfer rates up to 100 Mbps, it ensures rapid and reliable communication between devices. Siemens Mall
  • Flexibility: The system supports a wide range of modules, enabling tailored configurations to meet specific project requirements. Digi-Key

SIMATIC HMI MTP1000 Unified Comfort Panel

The SIMATIC HMI MTP1000 is a high-performance Human-Machine Interface (HMI) panel that provides intuitive operation and monitoring of industrial processes. Its notable features include:

  • Touch Operation: The 10.1-inch widescreen TFT display supports touch input, offering user-friendly interaction with the system. Siemens Mall
  • High-Resolution Display: With 16 million colors, it delivers clear and detailed visualizations, enhancing user experience. Siemens Mall
  • PROFINET Interface: The integrated PROFINET interface ensures seamless communication within the network, facilitating efficient data exchange. Siemens Mall

These components were integral to the project's success, providing robust control and monitoring capabilities essential for the AFU system's operation. Their advanced features and reliability contributed significantly to meeting the project's objectives and ensuring long-term performance.

For more detailed specifications, please refer to the official Siemens product pages:

Feedback During Acceptance Testing

Factory Acceptance Testing (FAT):

Conducted internally at Ultech Engineering’s office, FAT received no direct client feedback.

Site Acceptance Testing (SAT):

Throughout the project, Ultech Engineering’s efforts were well-received. During the Site Acceptance Testing (SAT), feedback from the client included suggestions to enhance functionality and improve hardware. These inputs were swiftly implemented, ensuring the client’s expectations were not only met but exceeded.

  • Hardware: Clients requested all motorized fire dampers on a specific elevation to close when a fire was detected. Additionally, the MCB for the RIO1 panel was replaced with an original part to address tripping issues.
  • Software: SCADA/HMI systems were updated to include legends for icons and colors across screens.

Benefits of the Implementation of the Air Filtration Unit (AFU) system to the Client

The implementation of the Air Filtration Unit (AFU) system provided Sarawak Energy Sdn. Bhd. with a reliable air supply to critical rooms. This advancement enhanced operational efficiency and safety at the Bakun HEP.

Post-Handover Support: Employee Training and Ongoing Support Activities

Following project completion in January 2024, Ultech Engineering provided the client with operational manuals for SCADA and HMI systems. Training sessions conducted by Automation Head Engineer Wang ensured the client’s team was well-equipped to manage the new systems and ensure sustained performance.

Ongoing support activities for the future demonstrate our dedication to service excellence and they include:

  • Regular follow-ups to address operational concerns.
  • Technical assistance to optimize system performance.

Concluding The Bakun Pressurization Project

The Bakun Pressurization project underscores Ultech Engineering’s commitment to excellence in delivering turnkey engineering solutions. By overcoming logistical, environmental, and interpersonal challenges with better planning and effective project management techniques, the team successfully commissioned a cutting-edge VAC system, AFU control unit, that meets the client’s needs. This accomplishment not only strengthens Ultech Engineering’s reputation but also reinforces its position as a leader in the engineering industry.

Watch This Content On YouTube!

Contact Us to Power Your Automation and Upgrade Your Control Systems Today!

LIKE WHAT YOU SEE? GET IN TOUCH.
ADDRESS
1504, Piasau Industrial Estate, 98000 Miri, Sarawak, Malaysia
EMAIL
info@ultech-engineering.com
PHONE
+60 85-654 133
SOCIAL
Copyright © 2024 Ultech Engineering Sdn. Bhd. All Rights Reserved
magnifier linkedin facebook pinterest youtube rss twitter instagram facebook-blank rss-blank linkedin-blank pinterest youtube twitter instagram